Finish What We Started, Build the Future at NUI.

Latest Updates

Phase 3 is Underway! Thanks to your generosity, we’ve started Stage 01.
Let’s keep the momentum going together!

Where we are?

Stage 01July 2025 - September 2025

Construction Staging

• Excavation, utilities
• Basement walls
• Foundation for the entire first floor

Funding Completed
Stage 02October 2025 -May 2026

Exterior Construction & Gym

• Structural Steel
• Exterior walls &
roofing
• Completed & fully
functional gym

Funding Completed
Stage 03June 2026 - October 2026

First Floor Construction

• Cafeteria
• Kitchen
• Classrooms
• Offices
• Daycare

Funding Completed
Stage 04November 2026 - March 2027

Second Floor Construction

• Classrooms
• Offices
• Labs

Funding Completed
Stage 05April 2027 - September 2027

Final Stage Basement

• Library
• Art Room
• Storage

Funding Completed

What Is Phase 3?

Phase 3 is the final step in completing NUI’s permanent campus. This expansion will add dedicated classrooms, a gymnasium, and multi-purpose spaces designed to serve our growing student body and community. With your support, we can create a lasting environment for faith, learning, and leadership.

NUI Through The Years

Groundbreaking Pictures

Programs & Initiatives at Noor-ul-Iman School

At Noor-ul-Iman, our programs go beyond academics — they nurture the heart, mind, and soul. From Quran memorization and Islamic studies to leadership training, community service, and academic enrichment, each initiative is designed to develop confident, compassionate, and purpose-driven individuals rooted in faith and excellence.