Opens in a new tab

Finish What We Started, Build the Future at NUI.

Latest Updates

Phase 3 is Underway! Thanks to your generosity, we’ve started Stage 01.
Let’s keep the momentum going together!

Phase 3

Where We Are

The foundation is in and steel is going up. Here is what is done, what is underway, and what each remaining stage will cost.

Updated October 2026

Phase 3 by stage

Each block is sized by its cost.

Funded Current focus Still to come

Stage 1A

Site work, foundation and steel

Fully funded

Work completed

  • Grading, site utilities, underground utilities
  • Excavation and soil export
  • Foundation for the entire first floor

In progress now

  • Basement walls and basement slab on grade
  • Structural steel
  • Slab on grade
$4 Million Total cost of completed and in-progress work. Already accounted for, and the funds are in hand to pay for it.

Our focus right now

$5 Million gets us the gym and cafeteria

Two stages stand between today and a finished gym and cafetorium our students can use.

Stage 1B

Core and shell

$2MEstimate

  • Core and shell
  • Walls and roofing
  • Sprinklers, fire alarms, electrical work

Stage 2A

Gym and cafetorium

$3MEstimate

  • Entire gym
  • Entire cafetorium
Donate Now Every dollar raised now goes toward this $5 Million goal.

Still to come

Stage 2B

Rest of the first floor

$1.5MEstimate

  • Classrooms
  • Kitchen
  • Remaining areas of the first floor

Stage 3

Second floor and basement

$4MEstimate

  • Entire second floor classrooms
  • Offices, day care, labs and more
  • Entire basement finish

Where we are?

Stage 01July 2025 - September 2025

Construction Staging

• Excavation, utilities
• Basement walls
• Foundation for the entire first floor

Funding Completed
Stage 02October 2025 -May 2026

Exterior Construction & Gym

• Structural Steel
• Exterior walls &
roofing
• Completed & fully
functional gym

Funding Completed
Stage 03June 2026 - October 2026

First Floor Construction

• Cafeteria
• Kitchen
• Classrooms
• Offices
• Daycare

Funding Completed
Stage 04November 2026 - March 2027

Second Floor Construction

• Classrooms
• Offices
• Labs

Funding Completed
Stage 05April 2027 - September 2027

Final Stage Basement

• Library
• Art Room
• Storage

Funding Completed

What Is Phase 3?

Phase 3 is the final step in completing NUI’s permanent campus. This expansion will add dedicated classrooms, a gymnasium, and multi-purpose spaces designed to serve our growing student body and community. With your support, we can create a lasting environment for faith, learning, and leadership.

NUI Through The Years

Groundbreaking Pictures

Programs & Initiatives at Noor-ul-Iman School

At Noor-ul-Iman, our programs go beyond academics — they nurture the heart, mind, and soul. From Quran memorization and Islamic studies to leadership training, community service, and academic enrichment, each initiative is designed to develop confident, compassionate, and purpose-driven individuals rooted in faith and excellence.